Emergency power
About emergency power22,000-litre port tank: from ISO 20/19/19 to 16/14/11 in under a month
20/19/1916/14/11
ISO 4406 cleanliness code (requirement: 18/16/13)
Read the case478 kW Perkins generator: 8.5 % less NOx on the same diesel, just cleaned
684.9628.0
NOx at 100 % load, corrected (ppm)
Read the caseData centre: two standby power tanks from critical to approved in six days
23/23/2215/13/10
ISO 4406 cleanliness code (requirement: 18/16/13)
Read the caseDX1001-T-PT: 95.45 % fewer particles in the diesel in a single pass
21/19/1716/15/15
ISO 4406 at start (before and after the filter)
Read the caseNovium: diesel bug from 100,000 bacteria to 0, documented by the laboratory
100,0000
Bacteria (count)
Read the caseCranes and ports
About cranes and portsMarine and offshore
About marine and offshoreDrilling platform: compressor oil from MPC 43.0 to 6.1 in full operation
43.06.1
MPC (varnish potential)
Read the caseFerry fuel: from too dirty to measure to ISO 16/14/11
20/18/1216/14/11 after filtration
ISO 4406, fuel as delivered to the bunker barge (requirement: 18/16/13)
Read the caseMS Østerbris: 99.1 % of the water out of the hydraulic oil in a single pass
4,90987
Water in the reservoir (ppm)
Read the caseTanker fleet: main engine lube oil from ISO 19/19/16 to 15/15/13
19/19/1615/15/13
ISO 4406 cleanliness code
Read the caseManufacturing and industry
About manufacturing and industryORE Catapult: over 24 kg of sludge out of the hydraulic oil despite a 3 µm inline filter
in the oil despite a 3 µm inline filterover 24 kg removed
Sludge, varnish and debris removed in 6 months
Read the caseStadco: from weekly valve failures to two years without a single one
19/17/1214/12/09
ISO 4406 cleanliness code
Read the casePower generation
About power generation895 MW power station: MPC from 54.1 to 18.4, then rolled out on all three turbines
54.118.4
MPC (varnish potential), gas turbine 1
Read the caseCompressor oil in Aberdeen: varnish figure from 52.2 to 6.5
52.26.5
MPC (varnish potential)
Read the caseGT26 gas turbine: varnish figure from 52 to 8.4 in three months
528.4
MPC (varnish potential)
Read the caseSteam turbine in Greece: water from 392 to 46 ppm in 17 days
20/18/1417/15/11
ISO 4406 cleanliness code
Read the caseTransformer oil: breakdown voltage from 14 to 70 kV
14 kV70 kV
Breakdown voltage, IEC 60156 (minimum: 30 kV)
Read the caseGas engines and biogas
About gas engines and biogasEnovert: 7.2 times longer oil life and 41 fewer oil changes a year
about 487
Oil changes per year
Savings: about £80,000 in the first year, then about £68,000 a year
Read the caseGas engines on landfill gas: oil changes from about 150 to 650 operating hours
about 150 (weekly)650 on average
Oil change interval (operating hours)
Read the caseIndependent laboratory: the filtration does not remove the engine oil additives
3.13.8
Base number, BN (first and last sample)
Read the caseLandfill gas engines: 67 % fewer oil changes
67.4 %
fewer oil changes in the field test
Read the caseWind turbines
About wind turbines1.5 MW wind turbine: 3.8 kg of debris in one cartridge in 11 months
1128
Iron in the cartridge debris
Read the caseBonus 300 kW: new gear oil was black after 19 days, 51 days later it was clean
dark 19 days after the oil changevisibly clearer after 51 days
Oil appearance
Read the caseCondemned gear oil from a 2 MW wind turbine: 97.6 % fewer large particles
19,790473
Particles above 14 µm per ml
Read the caseGE wind turbine fleet: 91.5 % fewer particles in the gear oil across 28 gearboxes
11,100947
Particles above 4 µm per ml, average of 28 gearboxes
Read the caseSiemens 1.3 MW: 84 % less varnish in the gear oil while the turbine kept running
21/18/1115/14/11
ISO 4406 cleanliness code
Read the caseWind turbine gearbox: varnish figure from 57.1 to 3.2 in 120 days
57.13.2
MPC (varnish potential)
Read the caseMore documented figures
An independent test on a 478 kW Perkins generator measured 8.5 % less NOx and visibly less smoke, simply because the stored diesel was cleaned. For sites with environmental requirements and ESG reporting, that is a figure you can use directly.
At Novium, samples showed a bacterial count of over 100,000 before treatment. After treatment the count was 0, documented in reports before and after.
Get your own figures
Figures from other sites are good to know. Figures from your own are better. The pilot programme ends with a report with samples before and after.