Power station by the water
Power generation

GT26 gas turbine: varnish figure from 52 to 8.4 in three months

The varnish potential in a GT26 gas turbine had risen from 24 to 52 in one year. Three months after an offline filter was installed, the figure was 8.4, and the cleanliness code had fallen from ISO 18/17/12 to 15/13/10.

MPC (varnish potential)

528.4
84 %lower varnish potential (MPC)
3 monthsfrom installation to the reading of 8.4
CustomerPower station (not named by the manufacturer)
Countrynot stated
SystemGT26 gas turbine with 28,000 litres of lubricating oil, DX1006-T
FluidTurbine oil (Shell Turbo CC 46)

The lubricating oil in the power station’s GT26 gas turbine was monitored with regular oil samples. Over one year the varnish potential (MPC) rose from 24 in July 2023 to 38, 30 and finally 52 in May 2024. Varnish settles as a lacquer on valves and bearings, and in a turbine with 28,000 litres of oil an oil change is a major cost item.

On 7 May 2024 a Delta Xero DX1006-T was installed in a side loop on the turbine’s oil tank.

The samples over the following months showed MPC 21.3, then 16.8 and, on 1 August 2024, 8.4. The cleanliness code fell from ISO 18/17/12 to 15/13/10, and the ferrography, which had previously shown varnish particles of 1 to 6 µm, showed none.

The figures come from laboratory reports reproduced in the manufacturer’s case material; the laboratory is not named.

The figures before and after

MeasurementBeforeAfter
MPC (varnish potential)528.4
ISO 4406 cleanliness code18/17/1215/13/10
Varnish by ferrography1 to 6 µmnot detected

Read the full case study

The rest of the case study, with every before and after measurement, opens once you have entered your work email and company. You only need to do this once; then every case study on the site is open.

We only use the details to see which companies are reading. You will not receive newsletters, and we will not call you.